This project consists of piping modifications to improve pressure zones and water transmission capacity within the service area via the Washington Aqueduct water source. Modifications include construction of approximately 800 feet of 30-inch and 42-inch diameter water main, installation of new water flow meters, and interior pump station improvements. Construction limits are within Dolley Madison Boulevard and driveway of Fairfax Water’s Chain Bridge Pump Station, near the intersection of Kirby Road, as shown on the map above.
The new water main in Dolley Madison Boulevard will be located within Virginia Department of Transportation (VDOT) right-of-way. During construction, traffic will be maintained in both directions in Dolley Madison Boulevard at all times, although temporary lane closures and night work will occasionally be required. Work hours on Dolley Madison Boulevard will be limited to 9:30 am to 3:00 pm, Monday through Thursday and 9:30 pm to 2:00 pm on Friday. Night work, when required, will take place during the hours of 9:00 pm to 5:00 am, Monday through Friday. Construction of the project will last for approximately five (5) months.
Click here for more information regarding the typical water main construction process.
Construction Activities for March 2021:
- Pump Station will be placed back in service
- Restoration and final paving of Pump Station driveway
Project Schedule | |
---|---|
Start Construction | September 2020 |
Complete Construction | March 2021 |