The
Corbalis Water Treatment Plant is a state-of-the art water
treatment facility which provides potable water to nearly
1.5 million people in northern
Virginia. The facility was placed in service in 1982 and has
undergone several upgrades and expansions since then. To meet
the rising demand for water over the past two decades, the
facility’s capacity has been expanded from an initial 50 million
gallons per day to its current 150 million gallons per day
capacity. The current Stage III Development Project will
expand the plant’s capacity to 225 million gallons per day.
Corbalis Water Treatment Plant Stage III Expansion
Construction of the Stage III Development Project
began in the Spring of 2005 and is anticipated to be complete
in 2008. New facilities include an expanded Raw Water Control
Chamber, Carbon dosing facility, Flocculation-Sedimentation
basins, 75 MGD capacity granulated activated carbon filters
and a new sodium hypochlorite system for safer water
disinfection. There will also be 15 Million gallons of new on-site finished water storage
in an expanded underground clearwell. Construction is about
90% complete at this time.
Corbalis Stage III
Aerial view of Corbalis Water Treatment Plant showing Stage
III development.
Pond C Improvements
The Pond C improvements project is part of the Corbalis Stage
III Development Project. The project is currently 20% complete
with final completion scheduled for autumn 2009. The Pond C
project includes two decant basins, one chemical feed and pump
building, and a concrete liner for pond C.
Pond C Improvements
Aerial view of the Pond C improvements project at the Corbalis Water Treatment Plant.
Corbalis Water Treatment Plant
On-Site Power Generation
As part of Fairfax Water’s efforts to increase
system reliability during loss of commercial power, a standby
power generation facility will be constructed at the Corbalis
Water Treatment Plant site.
The generators will be housed in a specially designed structure
located partially below grade to reduce noise impacts to the
lowest levels. The structure will be screened from public view
by an earthen berm and visual buffer of mature and newly planted
trees.
Project documents will be available to qualified bidders during
the summer of 2008 and once awarded, the anticipated
construction duration will be 30 months with a completion date
in 2011.
On-Site Power Generation
Artist's rendering of the generator housing at the Corbalis Water Treatment Plant.